This procedure is for vertical roller mills (VRM) processing ATH, with special controls for low‑iron requirements, ATEX dust safety, stable material bed, and prevention of vibration / PSD drift. It follows the maintenance standard from ath-mill.com.
Important distinction: you may replace only the roller tyre (wear sleeve) or the full roller assembly. For premium low‑iron ATH, the roller surface coating, seal integrity and bearing cleanliness are critical to avoid iron contamination.
1. Pre‑work Safety & Preparation (mandatory for ATH)
- Full LOTO (Lockout / Tagout)
Stop feeder, mill main drive, ID fan, hydraulic station, lubrication system. Isolate electrical, hydraulic, compressed air and accumulator pressure; bleed hydraulic accumulators completely.
Purge the mill chamber with fan (doors closed) to remove suspended ATH dust; wait for mill temperature <40 °C before opening inspection doors. ATEX dust atmosphere check is required. - PPE and site protection
Hard hat, safety glasses, conductive dust respirator, anti‑static coverall, steel‑toe boots, anti‑static gloves. Use 36 V low‑voltage explosion-proof lighting inside the mill.
Keep the area clean; avoid creating large ATH dust clouds. No open flame inside the mill. - Spare part inspection (ATH low‑iron focus)
- Verify new roller tyre / full assembly drawing number, surface coating (hard alloy / ceramic coating for low‑iron grade), dimensions, roundness.
- Check for casting cracks, coating spalling, burrs.
- Prepare new seals, O‑rings, gaskets, lubricant, expansion sleeves, torque chart, hydraulic tools, lifting sling, hoist, turning cylinder kit.
- Record baseline data before disassembly
Measure roller gap, roller tyre diameter, table liner wear profile, hydraulic pressure setting, vibration trend, D97 and circulating load. Take photos of roller position, rocker arm connection and seal arrangement.
2. Position the roller for maintenance
- Start the hydraulic station (only after LOTO is confirmed and only for positioning). Lift the roller 50–100 mm above the grinding table, do not exceed the manufacturer’s limit.
- Install mechanical safety blocks under the roller rocker arm to prevent accidental lowering (hydraulic failure protection).
- Connect the turning hydraulic cylinder to the rocker arm; slowly rotate the roller assembly outward to the maintenance access position. Lock the rocker arm with mechanical pins after positioning.
- Remove inspection door, roller guard, dust shield and seal protective cover.
3. Disconnect service lines and sensors
- Disconnect roller bearing lubrication oil lines, temperature RTD / PT100 cables, seal purge air tubing. Cap all oil and air ports immediately to prevent ATH dust ingress into bearings.
- Mark all cables and hoses for reconnection; label each port.
- Remove debris and caked ATH around the roller hub and rocker arm joint.
4. Remove the old roller assembly / roller tyre
Option A: Replace full roller assembly
- Loosen rocker arm connecting bolts or expansion sleeve bolts in a symmetrical cross pattern (do not release all bolts on one side at once).
- Attach the certified sling to the designated lifting lugs on the roller housing; keep the load balanced.
- Separate the taper / expansion sleeve connection slowly with hydraulic pushers.
- Lift the roller out through the maintenance opening and place it on a stable maintenance stand.
Option B: Replace only the roller tyre (sleeve change, on or off line)
- Secure the roller core on a fixture. Remove end caps, retaining rings and pressure blocks.
- Use dedicated hydraulic pullers to push the worn tyre off the hub.
- Inspect the roller core, hub, bearing and labyrinth seal. If the core has scratches or corrosion, it will introduce iron contamination for ATH — replace or repair before reassembly.
- Clean the hub seating surface thoroughly; remove old residue and burrs.
ATH note: Do not use steel wire brushes on the hub surface for low‑iron grades; use non‑ferrous scrapers and conductive vacuum.
5. Assemble the new roller
- For tyre replacement: heat the tyre following the supplier’s temperature limit (controlled induction heating only; avoid overheating coating). Slide onto the hub, install locking blocks and retainers. Cool evenly before torqueing.
- Lift the new roller assembly carefully and align it to the rocker arm taper / expansion sleeve seat.
- Fit the expansion sleeve; align the opening direction per drawing.
- Tighten expansion sleeve bolts in multiple incremental passes, cross sequence, to the exact torque value. Uneven torque will cause roller wobble, vibration and uneven ATH grinding bed.
- Reinstall bearing end caps, new O‑rings and face seals. Apply compatible lubricant to seal lips.
- Reconnect lubrication lines, temperature sensors and seal purge air lines. Remove temporary caps.
6. Return roller to operating position and clear locks
- Double-check all tools, slings, debris are removed from the mill chamber.
- Remove mechanical safety pins and blocks from the rocker arm.
- Use the turning cylinder to swing the roller back to the grinding position.
- Lower the roller slowly until the tyre lightly touches the grinding table liner. Do not drop it.
- Reinstall dust guards, inspection door and gaskets; tighten door bolts evenly to prevent ATH dust leakage.
7. Post‑replacement inspection and commissioning checklist (ATH critical)
- Manual check: roller spins freely without binding, rubbing or scraping the table / nozzle ring.
- Seal test: turn on seal purge air, confirm no air leakage and no powder ingress path.
- Hydraulic test: pressurize the hydraulic system gradually, stepwise, check hoses, joints and rocker arm for leaks.
- Remove LOTO locks only after all personnel are clear of the mill interior.
- No-load dry run (no ATH feed): 30–60 minutes. Monitor:
- Roller bearing temperature
- Mill vibration
- Abnormal noise
- Oil flow and pressure
- Seal leakage
If vibration rises immediately, the common root is uneven expansion sleeve torque, misalignment or out-of-round tyre.
- Low-load ramp-up: start at reduced feed rate, build material bed slowly. ATH is prone to unstable bed if all rollers are not matched in diameter.
- Stabilize grinding pressure, then sample product: track D97, circulating load, motor current and temperature.
- If multiple rollers are replaced: match roller diameters as closely as possible. A large diameter mismatch creates uneven bed, high vibration, PSD swing and localized high iron wear.
8. ATH-specific pitfalls to avoid
- Mixing new and heavily mismatched roller diameters → unstable material bed, temperature spikes and PSD fluctuation
- Damaging ceramic/alloy coating during lifting or assembly → rising iron content and loss of whiteness
- Forgetting to cap oil ports → ATH dust enters bearings and causes early bearing failure
- Over-tightening expansion sleeves → hub deformation, roller seizure
- Skipping the no-load run → hard contact between roller and table liner before a stable ATH bed forms
- Poor seal reassembly → dust leakage and bearing contamination
9. Acceptance criteria after replacement
- Roller bearing temperature rise <25 °C above ambient
- Mill vibration within the baseline trend
- No seal purge air leakage or dust escape
- Stable material bed, no current surging
- D97 returns to target setpoint without repeated classifier speed adjustment